Horizon Office Plaza
At RiskCommercial Building

Horizon Office Plaza

Horizon Realty Angeles, Pampanga

Overall progress

47%

Current phase

Electrical

Next: Plumbing

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Grace Tan

Budget

₱88,000,000

Start Date

Jan 9, 2026

Target Date

Oct 25, 2026

Current Phase

Electrical

Timeline

135d remaining

AI summary (preview): Horizon Office Plaza is 47% complete and currently at risk. Risk score 65/100.

Delay reported

Weather

Heavy monsoon rains halted exterior work for several days.

Reported Jun 9, 2026 · Expected resolution Jun 17, 2026

Electrical — Wiring Inspection Passed
Electrical — Electrical Rough-In
Photo evidence
AR

Allan Rivera

Jun 11, 2026 · 4:30 PM

Electrical

Wiring Inspection Passed

Panel board installed and circuits labeled.

3 photosAt Risk
GT

Grace Tan

Jun 11, 2026 · 3:15 PM

MilestoneRoofing

Roof Completed

Metal roofing panels fitted and sealed.

3 photosOn Track
AR

Allan Rivera

Mar 20, 2026 · 7:00 AM

MilestoneFraming

Framing Completed

Wall framing up on the ground floor.

3 photosOn Track
GT

Grace Tan

Feb 24, 2026 · 4:15 PM

MilestoneFoundation

Foundation Completed

Rebar tied and inspected before pour.

3 photosOn Track
AR

Allan Rivera

Feb 1, 2026 · 1:45 PM

Excavation

Footings Dug

Footing trenches dug and inspected.

2 photosOn Track
GT

Grace Tan

Jan 10, 2026 · 7:15 AM

Site Preparation

Site Setup Complete

Survey markers placed and access road graded.

3 photosOn Track