Horizon Office Plaza
Horizon Realty Angeles, Pampanga
Overall progress
47%
Current phase
Electrical
Next: Plumbing
Manager
Grace Tan
Budget
₱88,000,000
Start Date
Jan 9, 2026
Target Date
Oct 25, 2026
Current Phase
Electrical
Timeline
135d remaining
AI summary (preview): Horizon Office Plaza is 47% complete and currently at risk. Risk score 65/100.
Delay reported
WeatherHeavy monsoon rains halted exterior work for several days.
Reported Jun 9, 2026 · Expected resolution Jun 17, 2026


Allan Rivera
Jun 11, 2026 · 4:30 PM
Wiring Inspection Passed
Panel board installed and circuits labeled.
Grace Tan
Jun 11, 2026 · 3:15 PM
Roof Completed
Metal roofing panels fitted and sealed.
Allan Rivera
Mar 20, 2026 · 7:00 AM
Framing Completed
Wall framing up on the ground floor.
Grace Tan
Feb 24, 2026 · 4:15 PM
Foundation Completed
Rebar tied and inspected before pour.
Allan Rivera
Feb 1, 2026 · 1:45 PM
Footings Dug
Footing trenches dug and inspected.
Grace Tan
Jan 10, 2026 · 7:15 AM
Site Setup Complete
Survey markers placed and access road graded.