All projects

On TrackResidential House
Sampaguita Heights
The Cruz Family Iloilo City
Overall progress
35%
Current phase
Roofing
Next: Electrical
Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover
Manager
Dennis Lim
Budget
₱5,100,000
Start Date
Jan 26, 2026
Target Date
Jan 22, 2027
Current Phase
Roofing
Timeline
224d remaining
AI summary (preview): Sampaguita Heights is 35% complete and currently on track. Risk score 22/100.
BF
Boy Fernandez
Jun 9, 2026 · 1:15 PM
MilestoneFraming
Framing Completed
Roof trusses installed and braced.
2 photosOn Track
DL
Dennis Lim
Jun 9, 2026 · 10:00 AM
MilestoneRoofing
Roof Completed
Roof completed and waterproofing applied.
3 photosOn Track
DL
Dennis Lim
Mar 23, 2026 · 9:45 AM
MilestoneFoundation
Foundation Completed
Concrete foundation poured and curing.
2 photosOn Track
FA
Ferdie Aguilar
Feb 21, 2026 · 11:45 AM
Excavation
Footings Dug
Soil compaction tested and approved.
2 photosOn Track
DL
Dennis Lim
Jan 27, 2026 · 4:00 PM
Site Preparation
Site Setup Complete
Site cleared and fenced. Temporary facilities set up.
3 photosOn Track