All projects
Vista Verde Warehouse
DelayedWarehouse

Vista Verde Warehouse

FreshMart Distribution Mandaluyong

Overall progress

22%

Current phase

Foundation

Next: Framing

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Rafael Domingo

Budget

₱41,000,000

Start Date

Apr 12, 2026

Target Date

Nov 15, 2026

Current Phase

Foundation

Timeline

156d remaining

AI summary (preview): Vista Verde Warehouse is 22% complete and currently delayed. Risk score 79/100.

Delay reported

Inspection Delay

Awaiting structural inspection sign-off before proceeding.

Reported Jun 3, 2026 · Expected resolution Jun 19, 2026

Foundation — Foundation Poured
Foundation — Foundation Completed
Photo evidence
RD

Rafael Domingo

Jun 10, 2026 · 8:30 AM

MilestoneFoundation

Foundation Completed

Concrete foundation poured and curing.

3 photosDelayed
AR

Allan Rivera

Jun 7, 2026 · 7:15 AM

Excavation

Footings Dug

Soil compaction tested and approved.

3 photosOn Track
RD

Rafael Domingo

Apr 12, 2026 · 1:00 PM

Site Preparation

Site Setup Complete

Site inspection passed. Ready for excavation.

2 photosOn Track