All projects
Skyline Heights Tower
On TrackApartment Building

Skyline Heights Tower

Sunrise Property Holdings Makati

Overall progress

54%

Current phase

Electrical

Next: Plumbing

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Joana Santos

Budget

₱78,000,000

Start Date

Dec 31, 2025

Target Date

Oct 7, 2026

Current Phase

Electrical

Timeline

117d remaining

AI summary (preview): Skyline Heights Tower is 54% complete and currently on track. Risk score 7/100.

JS

Joana Santos

Jun 9, 2026 · 12:15 PM

MilestoneRoofing

Roof Completed

Roof completed and waterproofing applied.

3 photosOn Track
AR

Allan Rivera

Jun 6, 2026 · 4:45 PM

Electrical

Wiring Inspection Passed

Panel board installed and circuits labeled.

3 photosOn Track
TN

Toto Navarro

Mar 17, 2026 · 10:45 AM

MilestoneFraming

Framing Completed

Second-floor framing completed on schedule.

3 photosOn Track
JS

Joana Santos

Feb 21, 2026 · 8:15 AM

MilestoneFoundation

Foundation Completed

Rebar tied and inspected before pour.

2 photosOn Track
ES

Erwin Salazar

Jan 26, 2026 · 12:15 PM

Excavation

Footings Dug

Footing trenches dug and inspected.

4 photosOn Track
JS

Joana Santos

Jan 5, 2026 · 7:30 AM

Site Preparation

Site Setup Complete

Site inspection passed. Ready for excavation.

2 photosOn Track