Skyline Heights Tower
Sunrise Property Holdings Makati
Overall progress
54%
Current phase
Electrical
Next: Plumbing
Manager
Joana Santos
Budget
₱78,000,000
Start Date
Dec 31, 2025
Target Date
Oct 7, 2026
Current Phase
Electrical
Timeline
117d remaining
AI summary (preview): Skyline Heights Tower is 54% complete and currently on track. Risk score 7/100.
Joana Santos
Jun 9, 2026 · 12:15 PM
Roof Completed
Roof completed and waterproofing applied.
Allan Rivera
Jun 6, 2026 · 4:45 PM
Wiring Inspection Passed
Panel board installed and circuits labeled.
Toto Navarro
Mar 17, 2026 · 10:45 AM
Framing Completed
Second-floor framing completed on schedule.
Joana Santos
Feb 21, 2026 · 8:15 AM
Foundation Completed
Rebar tied and inspected before pour.
Erwin Salazar
Jan 26, 2026 · 12:15 PM
Footings Dug
Footing trenches dug and inspected.
Joana Santos
Jan 5, 2026 · 7:30 AM
Site Setup Complete
Site inspection passed. Ready for excavation.