Northgate Apartments
On TrackApartment Building

Northgate Apartments

BGC Ventures Inc. Taguig (BGC)

Overall progress

41%

Current phase

Roofing

Next: Electrical

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Carlo Mendoza

Budget

₱52,000,000

Start Date

Feb 6, 2026

Target Date

Oct 30, 2026

Current Phase

Roofing

Timeline

140d remaining

AI summary (preview): Northgate Apartments is 41% complete and currently on track. Risk score 7/100.

FA

Ferdie Aguilar

Jun 11, 2026 · 8:45 AM

MilestoneFraming

Framing Completed

Roof trusses installed and braced.

3 photosOn Track
CM

Carlo Mendoza

Jun 10, 2026 · 4:15 PM

MilestoneRoofing

Roof Completed

Metal roofing panels fitted and sealed.

2 photosOn Track
CM

Carlo Mendoza

Mar 28, 2026 · 11:00 AM

MilestoneFoundation

Foundation Completed

Rebar tied and inspected before pour.

2 photosOn Track
RC

Ronnie Castillo

Mar 4, 2026 · 2:00 PM

Excavation

Footings Dug

Soil compaction tested and approved.

2 photosOn Track
CM

Carlo Mendoza

Feb 10, 2026 · 10:00 AM

Site Preparation

Site Setup Complete

Site inspection passed. Ready for excavation.

3 photosOn Track