
Mabuhay Commercial Center
Metro Foods Corp. Cebu City
Overall progress
38%
Current phase
Roofing
Next: Electrical
Manager
Andrea Cruz
Budget
₱96,000,000
Start Date
Jan 26, 2026
Target Date
Dec 15, 2026
Current Phase
Roofing
Timeline
186d remaining
AI summary (preview): Mabuhay Commercial Center is 38% complete and currently at risk. Risk score 56/100.
Delay reported
WeatherHeavy monsoon rains halted exterior work for several days.
Reported Jun 5, 2026 · Expected resolution Jun 15, 2026


Andrea Cruz
Jun 8, 2026 · 9:45 AM
Roof Completed
Roof sheathing installed.
Toto Navarro
Jun 6, 2026 · 8:15 AM
Framing Completed
Wall framing up on the ground floor.
Andrea Cruz
Mar 17, 2026 · 11:45 AM
Foundation Completed
Rebar tied and inspected before pour.
Erwin Salazar
Feb 20, 2026 · 9:30 AM
Footings Dug
Excavation completed to design depth.
Andrea Cruz
Jan 27, 2026 · 8:15 AM
Site Setup Complete
Site inspection passed. Ready for excavation.