All projects
Casa Bella Renovation
On TrackRenovation

Casa Bella Renovation

Robert & Cecilia Lim Davao City

Overall progress

82%

Current phase

Finishing

Next: Landscaping

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Paolo Villanueva

Budget

₱2,800,000

Start Date

Mar 15, 2026

Target Date

Jun 9, 2026

Current Phase

Finishing

Timeline

3d overdue

AI summary (preview): Casa Bella Renovation is 82% complete and currently on track. Risk score 14/100.

PV

Paolo Villanueva

Jun 10, 2026 · 4:30 PM

Finishing

Painting Underway

Interior painting first coat applied.

2 photosOn Track
TN

Toto Navarro

Jun 10, 2026 · 10:45 AM

Drywall

Taping Completed

Ceiling boards installed and sanded.

3 photosOn Track
PV

Paolo Villanueva

May 2, 2026 · 1:15 PM

Plumbing

Pressure Test Passed

Plumbing rough-in for all wet areas done.

2 photosOn Track
JP

Jun Pascual

Apr 27, 2026 · 2:00 PM

Electrical

Wiring Inspection Passed

Panel board installed and circuits labeled.

3 photosOn Track
PV

Paolo Villanueva

Apr 20, 2026 · 4:45 PM

MilestoneRoofing

Roof Completed

Roof completed and waterproofing applied.

3 photosOn Track
BF

Boy Fernandez

Apr 14, 2026 · 7:00 AM

MilestoneFraming

Framing Completed

Roof trusses installed and braced.

3 photosOn Track
PV

Paolo Villanueva

Mar 31, 2026 · 9:00 AM

MilestoneFoundation

Foundation Completed

Concrete foundation poured and curing.

2 photosOn Track
RC

Ronnie Castillo

Mar 27, 2026 · 4:00 PM

Excavation

Footings Dug

Soil compaction tested and approved.

2 photosOn Track
PV

Paolo Villanueva

Mar 18, 2026 · 3:45 PM

Site Preparation

Site Setup Complete

Survey markers placed and access road graded.

2 photosOn Track