All projects
Riverside Townhomes
On TrackResidential House

Riverside Townhomes

Greenfield Developers Pasig

Overall progress

73%

Current phase

Drywall

Next: Finishing

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Mae Bautista

Budget

₱18,500,000

Start Date

Dec 10, 2025

Target Date

Aug 14, 2026

Current Phase

Drywall

Timeline

63d remaining

AI summary (preview): Riverside Townhomes is 73% complete and currently on track. Risk score 20/100.

MB

Mae Bautista

Jun 12, 2026 · 7:15 AM

Plumbing

Pressure Test Passed

Plumbing rough-in for all wet areas done.

3 photosOn Track
TN

Toto Navarro

Jun 11, 2026 · 7:15 AM

Drywall

Taping Completed

Taping and skim coat completed.

4 photosOn Track
TN

Toto Navarro

Apr 7, 2026 · 9:15 AM

Electrical

Wiring Inspection Passed

Wiring inspection passed.

3 photosOn Track
MB

Mae Bautista

Mar 13, 2026 · 4:30 PM

MilestoneRoofing

Roof Completed

Metal roofing panels fitted and sealed.

2 photosOn Track
JP

Jun Pascual

Feb 17, 2026 · 2:45 PM

MilestoneFraming

Framing Completed

Wall framing up on the ground floor.

2 photosOn Track
MB

Mae Bautista

Jan 25, 2026 · 3:30 PM

MilestoneFoundation

Foundation Completed

Rebar tied and inspected before pour.

2 photosOn Track
JP

Jun Pascual

Jan 3, 2026 · 1:45 PM

Excavation

Footings Dug

Footing trenches dug and inspected.

2 photosOn Track
MB

Mae Bautista

Dec 16, 2025 · 11:15 AM

Site Preparation

Site Setup Complete

Site cleared and fenced. Temporary facilities set up.

3 photosOn Track