Palms Residence
On TrackResidential House

Palms Residence

The Tan Family Bacoor, Cavite

Overall progress

91%

Current phase

Landscaping

Next: Turnover

Site Preparation
Excavation
Foundation
Framing
Roofing
Electrical
Plumbing
Drywall
Finishing
Landscaping
Turnover

Manager

Liza Garcia

Budget

₱6,200,000

Start Date

Sep 29, 2025

Target Date

Jun 29, 2026

Current Phase

Landscaping

Timeline

17d remaining

AI summary (preview): Palms Residence is 91% complete and currently on track. Risk score 28/100.

FA

Ferdie Aguilar

Jun 8, 2026 · 11:15 AM

Landscaping

Hardscape Poured

Driveway and walkways poured.

2 photosOn Track
LG

Liza Garcia

Jun 7, 2026 · 11:30 AM

Finishing

Painting Underway

Cabinetry and fixtures being installed.

4 photosOn Track
RC

Ronnie Castillo

Mar 23, 2026 · 2:45 PM

Drywall

Taping Completed

Taping and skim coat completed.

3 photosOn Track
LG

Liza Garcia

Feb 28, 2026 · 3:15 PM

Plumbing

Pressure Test Passed

Drainage and vent stacks installed.

2 photosOn Track
FA

Ferdie Aguilar

Jan 31, 2026 · 1:30 PM

Electrical

Wiring Inspection Passed

Electrical rough-in completed.

2 photosOn Track
LG

Liza Garcia

Jan 11, 2026 · 12:00 PM

MilestoneRoofing

Roof Completed

Roof sheathing installed.

4 photosOn Track
ML

Marco Lopez

Dec 13, 2025 · 11:00 AM

MilestoneFraming

Framing Completed

Wall framing up on the ground floor.

4 photosOn Track
LG

Liza Garcia

Nov 19, 2025 · 9:15 AM

MilestoneFoundation

Foundation Completed

Foundation completed. Ready for framing tomorrow.

2 photosOn Track
BF

Boy Fernandez

Oct 25, 2025 · 11:45 AM

Excavation

Footings Dug

Soil compaction tested and approved.

2 photosOn Track
LG

Liza Garcia

Oct 2, 2025 · 7:00 AM

Site Preparation

Site Setup Complete

Site cleared and fenced. Temporary facilities set up.

2 photosOn Track