Palms Residence
The Tan Family Bacoor, Cavite
Overall progress
91%
Current phase
Landscaping
Next: Turnover
Manager
Liza Garcia
Budget
₱6,200,000
Start Date
Sep 29, 2025
Target Date
Jun 29, 2026
Current Phase
Landscaping
Timeline
17d remaining
AI summary (preview): Palms Residence is 91% complete and currently on track. Risk score 28/100.
Ferdie Aguilar
Jun 8, 2026 · 11:15 AM
Hardscape Poured
Driveway and walkways poured.
Liza Garcia
Jun 7, 2026 · 11:30 AM
Painting Underway
Cabinetry and fixtures being installed.
Ronnie Castillo
Mar 23, 2026 · 2:45 PM
Taping Completed
Taping and skim coat completed.
Liza Garcia
Feb 28, 2026 · 3:15 PM
Pressure Test Passed
Drainage and vent stacks installed.
Ferdie Aguilar
Jan 31, 2026 · 1:30 PM
Wiring Inspection Passed
Electrical rough-in completed.
Liza Garcia
Jan 11, 2026 · 12:00 PM
Roof Completed
Roof sheathing installed.
Marco Lopez
Dec 13, 2025 · 11:00 AM
Framing Completed
Wall framing up on the ground floor.
Liza Garcia
Nov 19, 2025 · 9:15 AM
Foundation Completed
Foundation completed. Ready for framing tomorrow.
Boy Fernandez
Oct 25, 2025 · 11:45 AM
Footings Dug
Soil compaction tested and approved.
Liza Garcia
Oct 2, 2025 · 7:00 AM
Site Setup Complete
Site cleared and fenced. Temporary facilities set up.