Liberty Industrial Warehouse
Liberty Logistics Santa Rosa, Laguna
Overall progress
60%
Current phase
Plumbing
Next: Drywall
Manager
Noel Aquino
Budget
₱34,000,000
Start Date
Nov 6, 2025
Target Date
Oct 28, 2026
Current Phase
Plumbing
Timeline
138d remaining
AI summary (preview): Liberty Industrial Warehouse is 60% complete and currently on track. Risk score 26/100.
Noel Aquino
Jun 10, 2026 · 2:15 PM
Pressure Test Passed
Pressure test passed on supply lines.
Boy Fernandez
Jun 6, 2026 · 2:00 PM
Wiring Inspection Passed
Panel board installed and circuits labeled.
Noel Aquino
Mar 14, 2026 · 9:15 AM
Roof Completed
Roof completed and waterproofing applied.
Allan Rivera
Feb 12, 2026 · 2:30 PM
Framing Completed
Wall framing up on the ground floor.
Noel Aquino
Jan 11, 2026 · 2:45 PM
Foundation Completed
Rebar tied and inspected before pour.
Ronnie Castillo
Dec 12, 2025 · 3:15 PM
Footings Dug
Excavation completed to design depth.
Noel Aquino
Nov 12, 2025 · 1:15 PM
Site Setup Complete
Survey markers placed and access road graded.